Your GovernmentCity ServicesOur CommunityDoing BusinessHow Do I / Help Center
Click to Home

Go To Search
HomePrintEmail
Alerts
 


Translate
Oxbow Bluff Roundabout
June 8, 2018 Update:
The contractor for the roundabout at the Manor Road and Abbott Road intersection will continue to strip loam, stumps, subgrade and place gravels. In addition, the contractor will begin new storm sewer infrastructure and Liberty Utilities will begin relocating the existing gas main. Construction will require one lane alternating traffic at times controlled by flaggers. Slight delays should be expected.

June 1, 2018 Update:
The contractor will be grading and placing gravel along the south side of the intersection for the Roundabout at the Manor Road and Abbott Road intersection. All roads will remain open during the work. However, there may be delays at times to accommodate construction vehicles. Utility work is scheduled to begin the week of June 11, 2018.

May 25, 2018 Update:
The contractor will be stumping and grubbing within the work limits for the Roundabout at the Manor Road and Abbott Road intersection. In addition, gravel will be placed in preparation for the temporary reconfiguration of the intersection. All roads will remain open during the work. However, there may be delays at times to accommodate construction vehicles. No construction will occur on Memorial Day (5/28).

May 18, 2018 Update:
Tree clearing for the roundabout at the Manor Road and Abbott Road intersection will occur on Tuesday, May 22 and Wednesday, May 23. Work will require that Manor Road be closed between Sorrell Drive and Abbott Road between 7 a.m. and 5 p.m. both days. Delays and detours should be expected, and alternate routes should be used. Access for residents along this section of road will be accommodated.